Achieved 76% Pre-Manufactured Value (PMV): This indicates a high degree of offsite manufacturing, significantly reducing onsite construction time and labour.
Delivered the £60m facility to budget: The project was completed within the allocated budget, despite challenges such as post-COVID restrictions and material shortages.
Completed Phase 1 handover of Grade C cleanrooms in 17 months: The initial phase, including the cleanrooms, was delivered ahead of the overall project schedule, showcasing a remarkable acceleration in construction.
Total project duration of 22 months: The entire project was completed in 22 months, three years faster than the industry standard for similar facilities.
Certified as Zero Scope 1 Carbon Enabled, BREEAM Excellent and EPC-A Rated: The facility meets high environmental standards, with certifications reflecting its sustainability and energy efficiency.